Environmental impact assessment NPP Khmelnitsky-2/Rovno 4.
Project management
duration 01.09.1998 to- 30.11.1998
Research project (§ 26 & § 27)
Program none
Funder none
Competencies
Abstract
Assesment of the enviromental impact assessment for the nuclear power plant blocks Khmelnitsky-2 and Rovno 4 in the Ukraine with respect to meteorological and climatological aspects. Investigation of the possible consequences of a severe accident in Austria with Lagrangian particle dispersion model.
Project staff
Helga Kromp-Kolb
em.o.Univ.Prof. Dr.h.c. Helga Kromp-Kolb
helga.kromp-kolb@boku.ac.at
Project Staff
01.09.1998 - 30.11.1998
Petra Seibert
Assoc. Prof. Dr. Petra Seibert
petra.seibert@boku.ac.at
Tel: +43 1 47654-81417
Project Staff
01.09.1998 - 30.11.1998
BOKU partners
External partners
Austrian Institute for Applied Ecology
Antonia Wenisch
partner
University of Wienna, Institute of Risk Research
none
partner